Willsys would be using standard SAP Methodology SAP Homogenous/Heterogeneous System copy
The phases during the migration are as mentioned below:
Serial Number | Activity | Support Scope | Customer SCOPE |
---|---|---|---|
1 |
Install Operating System Win X86_64 |
Assist verbally and Remotely |
System Admin has to Install from Onsite |
2 |
File System Setup As per SAP Recommendations |
Assist verbally and Remotely |
System Admin has to setup from Onsite |
3 |
Order SAP Software |
Assist verbally or send message to SAP |
------- |
4 |
Download SAP Software from SAP Market Place |
Complete Scope |
------- |
5 |
Enable the Network and Provide Remote Access |
Assist verbally and Remotely |
System Admin has to enable the Remote connectivity, IP Address setup, add to Domain and allow in Firewall(if any) |
6 |
Provide IP Addresses |
Assist verbally and Remotely |
System Admin has to provide IP Addresses |
7 |
Install Database |
Install the SQL Server and Software and patches |
Copying the SQl Server Software along with patches |
8 |
Install SQL Server Patches |
Install SQL Patches |
Copying Software SQL patches |
9 |
Setup the Environment |
Support Partner sets the Environment |
Provide access to SAP |
10 |
Copy the SAP Software |
------- |
Copy the Software from CD or Download Area to Servers. |
11 |
Install the SAP ERP System on Development System with X-86 Environment |
Install the SAP System |
Allow the blocks to install on the specified ports. |
12 |
Perform the Post Installation Actions |
Apply License STMS |
------ |
13 |
Install GUI |
Install 740 GUI |
------ |
14 |
Checking the Sanity, High Availability and Network and Adding Entries to Presentation Servers |
Complete Scope |
Presentation Servers has to be modified by Customer System Admin and check the connectivity. |
15 |
Provide Access to End Users for testing |
Support Network Issues and remote connectivity |
------- |
16 |
Perform Backup |
Support Network Issues and remote connectivity |
------- |
Serial Number | Name of the Activity | No of Days |
---|---|---|
Install, configure and setup sap router of Solution Manager |
7 Days |
|
1 |
SAP ECC 6.0 Upgrade EHP6.0(Mock 1) |
15 Days |
2 |
Planning the Upgrade |
|
3 |
Documentation of the upgrade |
|
4 |
Preparation for the Upgrade |
|
5 |
Backup of Production Database |
|
6 |
DB Refresh on Quality/sandbox System |
|
7 |
Connect to Market Place through Solution Manager |
|
8 |
Configure Maintenance Optimizer |
|
9 |
Add the Software Downloads (Generate XML File) |
|
10 |
Download the Software |
|
11 |
Execute Prepare |
|
12 |
Upgrade Execution |
|
13 |
Communication with SAP to Resolve Runtime Issues |
|
14 |
Handling SPDD and SPAU Objects |
|
15 |
Testing the Upgrade |
|
Export the Database and import the Database(Unicode) |
||
Post Upgrade steps |
||
16 |
SAP ECC 6.0 Upgrade EHP6.0(Mock 2) |
10 Days |
17 |
Backup of Production Database |
|
18 |
DB Refresh on Quality System |
|
19 |
Connect to Market Place through Solution Manager |
|
20 |
Configure Maintenance Optimizer |
|
21 |
Add the Software Downloads |
|
22 |
Generate XML Stack File |
|
23 |
Execute Prepare |
|
24 |
Upgrade Execution |
|
25 |
Communication with SAP to Resolve Runtime Issues |
|
26 |
Handling SPDD and SPAU Objects |
|
27 |
Testing the Upgrade |
|
Export the Database and import the Database |
||
28 |
SAP ECC 6.0 Upgrade EHP6.0(DEV) |
10 Days |
29 |
Backup of Development Database |
|
30 |
Execute Prepare |
|
31 |
Connect to Market Place through Solution Manager |
|
32 |
Configure Maintenance Optimizer |
|
33 |
Add the Software Downloads |
|
34 |
Generate XML Stack File |
|
35 |
Upgrade Execution |
|
36 |
Communication with SAP to Resolve Runtime Issues |
|
37 |
Handling SPDD and SPAU Objects |
|
38 |
Generate Change Requests |
|
39 |
Testing the Upgrade |
|
Export the Database and import the Database |
||
Post Upgrade |
||
40 |
SAP ECC 6.0 Upgrade EHP6.0(PRD) |
3 Days |
41 |
Backup of Development Database |
|
42 |
Execute Prepare |
|
43 |
Connect to Market Place through Solution Manager |
|
44 |
Configure Maintenance Optimizer |
|
45 |
Add the Software Downloads |
|
46 |
Generate XML Stack File |
|
47 |
Upgrade Execution |
|
48 |
Handling SPDD and SPAU Objects |
|
49 |
Generate Change Requests |
|
50 |
Testing the Upgrade |
|
Export the Database and import the Database (Unicode |
||
Post Upgrade steps |
Note: The Above line Items provided in the above table has to be iterated as many times ( at least 2 times) as possible until the final miles stones are arrived for scheduling down time.
The Functional Team and Technical Team has to verify and certify the Systems before carrying out the Final Migration
Same Approach will be followed for Solution Manager and BI-BO Systems
Disaster Recovery Server will be set up from the Copy of Production Upgrade
we are here to help you!